Lamb Weston Facility- Boardman, OR

Lamb Weston Facility- Boardman, OR

lamb-weston-boardman-facility-001

We installed 2,700 precast pieces for this 192,000-square-foot, $220 million addition to Lamb Weston’s Boardman facility, allowing the company to expand its processing capabilities for frozen potatoes and other vegetables.

This was a complex project requiring a great deal of technical knowledge — we had to create the superstructure before the interior, and then create a structure within that structure. And design delays prevented us from starting the work until more than a month after we were initially scheduled to begin. Despite these issues, however, our speed helped us to “rescue” the project and meet the original target completion date.

CLIENT

LW Boardman Complex